ComEd contractor Intren is replacing underground cable in our area. Impacted residents should have received notification.
- The cable runs primarily in the rear of the properties in town
- The possible impact will be a couple of potholes in the backyard, which will be landscaped pending weather in December or Spring 2023.
- The contractor will be doing the work using directional drilling to minimize impact
- The work is scheduled to tentatively start at the end of November with a duration of approximately 3 weeks.
- There are no anticipated power interruptions associated with this work.